Sectional Title: Extensions involve lots of red tape

Sectional title (ST) property owners who would like to extend or alter their units to create more space will probably have to spend a considerable amount of time and money to get the necessary approvals.
 
Before they can begin any building work they will need:

· The approval of the body corporate, authorised by a special resolution of its members;
· The approval of every bondholder (bank) with an interest in the ST scheme if they intend extending the unit by more than 5% of its current area;
· An amended sectional plan and a new schedule of participation quotas (PQs), drawn by a land surveyor or an architect for submission to the Surveyor General and then registered in the Deeds Office;
· The approval of the local authority for the building work proposed, which can only be obtained after the changes to the sectional plan have been approved and registered.
 
It is worth noting, says Berry Everitt, MD of the Chas Everitt International property group, that approval to extend a section comes from the body corporate - not the trustees – and that a special resolution requires a 75% vote in favour (in number and PQs) by the members of the body corporate present or represented by proxy at a meeting at which a quorum is present and of which at least 30 days’ notice has been given.
 
“However, owners who want to extend their sections must pay all the legal and administrative costs of changing the sectional plan and getting it approved and registered themselves. This is not a body corporate expense.”
 
On the other hand, he says, there is no question of an owner who wishes to extend having to "buy” the land on which he or she plans the addition. “All land within an ST scheme forms part of the common property and is owned in undivided shares by all the members of the body corporate.”
 
Writing in the Property Signposts newsletter, Everitt says the benefit to the body corporate of any extension will come in the form of a higher levy paid by the owner as a result of the increase in the PQ resulting from the increase in the floor area of the section – and that this will apply even if the section is extended vertically rather than horizontally.


  Comment on this Article

  Please login to post comments

Post to my facebook wall
  
2000
Characters remaining


    Latest Property News
    • 18 Jan 2018
      The Southern Suburbs make up some of the most popular residential areas in Cape Town, comprising charming groups of suburbs which lie to the south-east of the slopes of Table Mountain. It is seen as the city's most expensive residential neighbourhoods with a choice of various private schools, upmarket eateries, wine estates, beautiful homes and trendy apartments.
    • 18 Jan 2018
      New year, new goals! If you’ve resolved to purchase your first property in 2018, then this 6-step guide from the Rawson Property Group is a must-read. It will help you navigate and simplify what is often be seen as a confusing process of buying your first home – right from the house-hunt to the house-warming.
    • 17 Jan 2018
      While the current property market may still favour buyers, it doesn’t mean that they shouldn’t be well prepared before putting in an offer to purchase.
    • 17 Jan 2018
      Lightstone lists Blair Atholl as the most expensive suburb with an average house price of R11.2 million, followed by Westcliff (R10.5 million), Dunkeld (R9.3 million), Sandhurst (R9.1 million) and Inanda (R7.2 million).
    • 17 Jan 2018
      As it currently stands, there are four main ways in which a home can be bought in South Africa, says Adrian Goslett, Regional Director and CEO of RE/MAX of Southern Africa, who adds that deciding in which legal entity to purchase the property is not a decision that should be entered into lightly, as each has its pros and cons.
    • 16 Jan 2018
      The start of the new year is symbolic of new beginnings. A good time to take stock of one’s possessions as well as how necessary they actually are. However, seeing as the process may appear daunting – a plan goes a long way.
    • 16 Jan 2018
      The Western Cape is still in the throes of a severe drought and many households have to adjust the way they use and save water. It is a little more complicated in sectional title schemes, however, as it is not that easy to implement grey water systems for multiple users and it is also difficult to monitor water usage accurately if there are no separate water meters
    • 15 Jan 2018
      In ideal rental situations, when a lease is signed the tenant will stay for the full duration of his lease without any complications and the landlord will uphold his obligations, creating a win-win situation for tenant and landlord.
        
    X
    Subscribe to the MyProperty Newsletter

    Name  
    Last Name  
    Email Address  
    Email Frequency
    select
    X
    Share this Page

       
    For Sale Property
    Rental Property
    More Options
    About
    Connect with us
    FEEDBACK